Council took up a $566,108.95 engineering agreement (80% reimbursable) and an amended PennDOT agreement raising the project cap to $4.61 million for the Allegheny River Green Boulevard project.
At a glance
- Total mentions
- 1
- Last 30 days
- 1
Discussed at 1 meeting in the last 60 days; most recently Nov 2, 2026.
Impact analysis
Project cap grows by $2.11 million to $4.61 million, mostly state-reimbursed; city share of some costs capped at $30,000.
Riverfront trail users and communities along the Allegheny corridor.